Kyushu Electric Power Co., Inc.
Genkai Nuclear Power Station
|
NSnet Peer Review for Kyushu Electric Power Co.,Inc. Genkai Nuclear Power Station was carried out over a four-day period starting December 12th.
The NSnet Peer Review team consisted of specialists from Hitachi, Ltd. , The Chugoku Electric Power Company, Inc. , Sumitomo Metal Mining Co., Ltd. , Chubu Electric Power Company, Inc. , Japan Nuclear Fuel Limited , as well as a secretariat staff (a total of six members). The review involved the assessments of the company's organization / administration, emergency measures, education / training, operation / maintenance, radiation protection, and addressing important issues associated through observations of those activities, interviews with employees, and examination of documents.
|